   header priority 1

 

 
    Through the planning process, the Planning Advisory team and the Executive Committee agreed that the solid condition of the existing Centennial Middle School facility would allow it to serve the District into the future. Priority 7 includes upgrades at this facility to improve interior finishes and to improve the interior space layout. Shared break-out spaces and 21st century learning environments will be created to allow improved learning and collaboration opportunities for students.    
         
    Identified Projects:    
         
   
 
  1. Building Renovation at Centennial Middle School
    Complete a building renovation to improve the interior learning environment. This will include reimagining the classroom clusters and their relationship to the common space between. The space between will be opened up to the corridor allowing access, views and connection with the learning going on in the learning pods. The common space between classrooms will be a flexible student centric space that will allow break-out, group work and collaboration between teams, classes, and small groups. Skylights will be added to bring natural light into the spaces that are internal to the building without window connection to the outside. This renovation will include interior finishes that are outdated. Sitework will include a defined outdoor dining courtyard and improved student circulation path between the two buildings. Sitework will also include improved grading and drainage around the building.
      1. Approximate Heavy Renovation Area: 18,000 sq. ft.
      2. Approximate Light Renovation Area: 30,000 sq. ft. (estimate)
      3. Additional Information
        1. Estimated Project Costs:
          • Construction Costs (from FCI):     $11,275,827
          • Owner Soft Costs (25%):               $2,818,956
          • Owner Contingency (15%):           $1,691,374
          • Total:                                             $15,786,157
        2. Concept Planning Construction Cost Estimate (by FCI)
 
   

 

Select from the Icons below for more information about each District Priority and identified improvement projects:

priority1 iconpriority2 iconpriority3 iconpriority4 iconpriority5 iconpriority6 iconpriority7 icon

 
 
  Welcome Page   Process Overview    Research & Investigation     Master Capital Plan     Implementation  
 
 
 

Quick Links / Additional Information

 
 

BEST Program Information
Colorado Department of Energy (CDE) Assessment
School District Website
Montrose Childcare Needs Assessment

 
     
  Thank you for taking the time to review and consider the Master Planning Process.
Feel free to share your thoughts by email with us at: feedback@mcsd.org